Welcome to the 200 & 400 North Sewer Replacement Project information site for Logan City, UT. Please check-in frequently to stay updated with the latest construction progress.
Project Underway!
Looking to replace your sewer service line?
We recommend taking advantage of this time to get your lateral line replaced! We have options for property owners to work with the project contractor to replace sewer lateral lines during the construction of this project.
ABOUT THE PROJECT
This city's sewer infrastructure along 400 & 200 North has significantly exceeded its serviceable life. As such, necessary improvements are essential to maintain a reliable sewer system for properties adjacent to the work.
FAQ
Pipelining vs. Pipeline Replacement
The difference between lining a sewer mainline and performing a full replacement primarily depends on the condition of the existing pipe. If the pipe maintains adequate capacity, proper alignment, and has no low spots, a less intrusive lining method can be used to extend its lifespan. However, if the pipe has settled, causing low spots and pooling, it must be excavated and replaced. Full replacement is also required in areas where the sewer pipe size needs to be increased.
What portion of the sewer pipeline is my responsibility?
The property owner owns the service lateral pipeline from the home/business all the way to the main pipeline. This includes the connection to the main pipeline. The service lateral pipeline length and alignment may vary slightly.
What are you doing to ensure crew, motorist and pedestrian safety in the construction zones.
For your safety, as well as the safety of those working in the area, please use extra caution and stay alert while driving through construction zones. In particular near areas with deep trenches during excavation. Businesses and residents in the area should anticipate increased noise, dust, and vibration associated with construction.
For pedestrian safety, please stay clear of construction equipment and work zones onsite. Pay attention to road closure signs and work areas zoned off by construction tape, barrels, cones or barricades.
Why are we replacing the sewer main pipeline?
We have historical and recent visual evidence of extremely high corrosion and deterioration levels. The volume of repairs are adding increased pressures on rates.
CONSTRUCTION SCHEDULE

200 North
Start: As early as Mar. 10th, starting on 200 N @ 600 W intersection
-
Phase 1 (March 17 - April): 600 West to 350 West
-
Phase 2 (April): 350 West to 200 West
-
Phase 3 (Late April - May): 200 West to Main Street
---------------------------------------------
400 North
Start: May 2025 (estimated)
---------------------------------------------
Days: Monday-Friday
Hours: Mostly Daylight hours, with occasional nighttime work
Estimated Project Completion: September 2025
Schedule is subject to change due to weather and materials available

200 North | Traffic Control Plan
Drivers should slow down and use caution!
-
Work occurs in the center turn & eastbound lane of 200 N
-
Only westbound traffic allowed in work zones
-
Shoulder parking restricted
-
Brief property access restrictions possible
400 North | Traffic Control Plan
-
Work occurs in the center turn & eastbound lanes of 400 N
-
Two-way traffic will remain enabled
-
Shoulder parking restricted
-
Brief residential/business access restrictions possible